Valley Water crews pictured Dec. 15 were excavating dirt and installing walls inside a 20-foot tunnel under construction through the bottom of Anderson Dam. Photo: Michael Moore

Projected costs of the massive Anderson Dam reconstruction project in Morgan Hill have risen to approximately $2.3 billion, according to a report prepared by engineers for the Santa Clara Valley Water District.

Two years ago, the cost of the dam project—required for earthquake protection and improved flood control for the Coyote Creek watershed—was estimated at $648 million. That nearly doubled last year, to $1.24 billion. The Valley Water board of directors is now looking at a new estimate of $2.3 billion, more than triple the 2021 price tag.

The draft cost estimate was submitted to the regional water district in September.

“Several factors contributed to the increase in the construction estimate,” the report said. “Risk reduction measures were added, such as the articulated concrete block auxiliary spillways for interim dams and a supplemental bid item for 1-year delay due to a shortened construction season.”

The new cost increase included increased design costs, construction roads and a new spillway design that lengthens the outlet tunnel under construction.

“Current market conditions have been incorporated into the construction cost to reflect significant increases in material costs, such as concrete and steel, and increases in assumed contractor markups for overhead and profit,” the report said.

The independent construction cost estimate was prepared by OCMI, Inc. and is anticipated to be submitted to Valley Water in December.

The new price tag includes $1.9 billion for the dam and spillway construction, plus approximately $400 million for related projects.

The completion date, 2032, has not changed.

The federal Environmental Protection Agency early this year announced $737 million in low-cost loans for the project, but the Valley Water board will be taking a new look at how to pay for the entire project, including possible increases in its wholesale and retail water rates.

Valley Water’s largest water reservoir has been drained to 3% levels.

Anderson Reservoir, built in 1950, is the largest of the 10 water district reservoirs and has a total storage capacity of 89,073 acre-feet (one acre-foot is 325,851 gallons of water, enough to serve two households of five for one year). 

Findings of the original seismic stability evaluation completed in 2011 on Anderson Dam indicated that the downstream and upstream embankments could become unstable during a very large magnitude earthquake.

Previous articleDeputies and Dogs 5K fundraiser set for Nov. 18 at Harvey Bear Ranch
Next articleMHPD receives $60K traffic safety grant from state

2 COMMENTS

LEAVE A REPLY

Please enter your comment!
Please enter your name here